An extension of the 12Barg / 250deg.C Superheated Steam line from an existing site system owned by Boots, to feed via new de-superheaters a new processing plant in the Reckitt Benckiser building. Pipe Solutions advised on the total control of thermal expansion, analysing the pipe stresses using Caesar II Software and supplying the necessary equipment for correct control of the expansion.

Mechanical Contractor: Brettex Engineering Ltd

Services Consultant: Lorien Engineering Solutions Ltd

Products Supplied:

  • Caesar II Pipe Stress Analysis
  • Expansion Joints
  • Guides
  • Skids
  • Anchors
  • Variable Spring Supports